Under a proposed new agreement, Fourways Mall's managers would earn 2.5% of approved project costs, which tells a contractor exactly whose phone to ring about the next refurbishment.

By the Arabella team


Retail refurbishment contractors in South Africa usually phone the wrong party. The fund owns the mall, but the fee schedule shows who lets the work. At Fourways Mall, under a proposed new agreement, the managers would earn 2.5% of approved project costs. That makes them the people with a reason to get projects built.

That reading is ours, not the fund's. Nothing Accelerate Property Fund has published says how refurbishment packages will be procured. But a fee schedule is a statement of who is paid to do what, and it is worth reading that way.

What was signed at Fourways Mall

Accelerate has signed a new agreement appointing Flanagan & Gerard and Luvon Investments as property manager, asset manager and development manager of Fourways Mall, it announced on SENS on 28 September 2026 (Property Wheel's report). The two firms have run the mall since February 2024. A 2024 agreement meant to formalise that lapsed. In August 2026 the JSE publicly censured Accelerate for letting them start without shareholder approval, and fined it R500 000, wholly suspended for three years.

This time the vote comes first. Shareholders must approve the agreement by 17 December 2026, and that condition cannot be waived. The co-owners were also due to provide a bank guarantee by 30 October 2026, a condition the managers can waive or defer. We have not found whether it was met. Everything below applies if the agreement goes ahead.

The mall is large. Its gross lettable area was 179 973m² at 31 August 2026, it was extensively refurbished between 2017 and 2019, and Accelerate's 50% share has been independently valued at about R4.2 billion.

Who do you actually phone about a mall refurbishment?

You phone the development manager, not the fund. An executive committee set up for the mall approves each project and its budget. The development manager is paid on the cost of those approved projects, and that is the party with a reason to get projects defined, approved and built.

The proposed fees make the split plain:

FeeRatePaid onWhat it rewards
Property management1%monthly collectionsrunning the building
Asset management1.75%monthly collectionsstrategy and income
Leasing0.5%monthly collectionsfilling space
Development management2.5%approved project costsprojects that get built

Three of the four fees grow with rent collected. One grows with construction spend. For a contractor, that fourth line is the one that matters. On every R10 million of approved project cost, the development management fee would be R250 000. Spend above the approved budget earns no fee.

The property management line matters too, for a different reason. Maintenance is funded from operating budgets, not project budgets. A mechanical contractor looking for a term maintenance contract speaks to property management. The same firm pitching a food court refit speaks to development management. They may sit in the same company and still be two different conversations.

The two managers may also earn an "upside participation fee" when the agreement ends, payable in cash or in a share of the mall. Separately, they get an option to buy up to 15% of the mall. Managers who may end up owning part of the asset have a reason to care how well it is built.

Why this mall and why now

Accelerate says the previous arrangement cut vacancies from 18.8% in February 2024 to 6.6% in August 2026. Tenant turnover rose from R226.3 million to R365.2 million over the same period. Falling vacancy means tenants moving in, and tenants moving in means tenant installations, shopfront work and services alterations.

It was not Accelerate's only deal in September. Three days earlier, on 25 September, it announced the sale of Wanooka Properties to Rand Mutual Assurance for R385 million, subject to conditions precedent. Wanooka owns KPMG Crescent and the adjacent parkade at 85 Empire Road in Parktown. KPMG's lease ends on 30 April 2027 and the firm moves to Sandton the following month. Space KPMG leaves needs assessing and reinstating before it can be let again.

New retail is still opening elsewhere. Twin City and GMI Property Group opened Malekane Mall in the Tubatse area on Heritage Day, about 19 000m² with more than 60 retailers. The developers say almost R20 million went to local labour and materials during construction. For the other end of the process, on how packages reach smaller firms, see the mall that used 17 SMMEs.

What a development manager checks before calling you

A development manager paid on approved cost carries the risk of a project that overruns or stalls. So the questions arrive before the price does. What is your cidb grading, and is it enough for this package? Who are your directors? Can you show three completed retail jobs with a reference who answers the phone?

If your grading is the gap, how to upgrade cidb grading sets out the timeline. If the paperwork is in order, the gap is usually being known to the right person early enough.

Arabella Infrastructure Solutions is a Johannesburg-based vetted contractor panel that introduces verified contractors to the managers who control refurbishment and maintenance budgets, so the checks are done before the first conversation. How that works for a contractor is on the contractor page.

On Monday

Take the three largest retail centres within an hour of your yard. For each, find out who holds the development management mandate and who holds property management. Those are six names, and on most centres nobody in your firm has spoken to any of them.

Comments

Leave a comment

Comments are read before they appear, and your email address is never published. If you are correcting a fact, say which one. It gets checked at the source and the piece gets amended.

Read next
Construction work in the R2 trillion pipeline
Site & delivery

Construction work in the R2 trillion pipeline

Of 263 projects worth R1,99 trillion, the 54 in documentation are the ones that become tenders. The 82 under construction are somebody else's order book.

Read→

Run a contracting firm?

Spend less time chasing tenders. Join the panel that brings you the work.

We win the work, match it to vetted contractors and manage the client, so you can stay on site. Apply online in a few minutes and we will set up a short meeting to take you through it.

The Arabella Brief

What changed this week, and what it costs you on Monday.

One email on a Friday, covering the week from Friday to Thursday so the week is closed when it is written. What actually changed, everything with a date on it, one development run through what it means for a contractor with forty people, and what we got wrong. A thin week is a short issue.

Friday. One email. Unsubscribe in one click. Privacy notice.